             For the purpose of ensuring timely completion of projects for facilitating optimal returns to the individual / mobilization members of cooperative societies, NCDC prescribes Milestone Chart as per model placed below.

 

MILESTONE CHART

 

S/GOVT.

DIRECT

 

INFRASTRUCTURE   MARGIN MONEY    WORKING CAPITAL

 

(Please Tick the appropriate box)

                                                                                                                                                            (Rs. in crore)

1.     Name of the Society

2.     Key Contacts (Name/Designation/Address/Tel. No./Fax No./E-mail)

          i)   ….  

          ii)  ….

3.    Description of the Project

4.    Date of receipt of proposal (i.e. START DATE)

5.    Block Cost  proposed

          NCDC’s Share (proposed):      Loan ______ Subsidy ______

          State Government’s Share:     Loan___ Share capital_____ Subsidy___

                                 Activity

No. of   days

 Date of Completion

Delay, if any

Remarks

1

2

3

4

5

1. Preliminary scrutiny / Consideration by Pre- Screening Committee/ Desk appraisal

 

 

15

 

 

 

2. Field appraisal

30

 

 

 

3. Consideration by Internal Screening Committee

10

 

 

 

4. Consideration by Board of Management

30

 

 

 

5. Draft sanction  letter with legal formats to be vetted by Legal Cell *

3

 

 

 

6. Issue of sanction letter

5

 

 

 

           (* In case of Direct Funding Only)